CONSTRUCTING A SUBSTATION
ᑲᐅᔑᒋᑲᑌᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ

 

There are 10 main steps in electrical substation construction.
ᐁᑲᐧ ᒥᑕᓱ ᑕᐦᑯᑭᐃᐧᓇᐣ ᑐᒋᑲᑌᐊᐧᐣ ᑲᐅᔑᒋᑲᑌᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ.


Picture1.jpg

STEP 1 | SURVEY & GEOTECHNICAL STUDIES
ᑕᐦᑯᑭᐃᐧᐣ 1 | ᓇᓇᑕᐃᐧᑭᑫᐣᒋᑫᐃᐧᐣ & ᑲᐃᐧᐃᔑᔭᑌᐠ ᓇᓇᑕᐃᐧᑭᑫᐣᒋᑫᐃᐧᐣ

Survey crews stake or flag the locations for the station using predetermined GPS coordinates.

ᐊᓄᑭᓇᑲᓇᐠ ᑭᑭᓇᐧᒋᒋᑫᐊᐧᐠ ᑲᐃᐧᐃᔑᐸᑕᑭᑌᑭᐣ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᔕᐣ ᐁᑲᐧ ᒪᒪᑕᐤ ᐱᐊᐧᐱᑯᐠ ᐅᑕᐸᒋᑐᓇᐊᐧ.


Picture2.jpg

STEP 2 | SITE CLEARING & GRADING
ᑕᐦᑯᑭᐃᐧᐣ 2 | ᐊᓄᑭᐃᐧᓂᐠ ᐸᐡᑲᐧᑕᐦᐃᑫᐃᐧᐣ & ᐊᐧᐁᐧᑕᐦᐃᓂᑫᐃᐧᐣ

The ground is cleared in preparation for construction of the substation pad. This stage may consist of logging, mulching, burning, and clearing of debris, as well as building access trails to the site.

ᐁᑲᐧ ᐊᐦᑭᑲᐠ ᐸᐡᑲᐧᑕᐦᐃᑲᓂᐊᐧᐣ ᐁᑲᐧᔭᒋᒋᑲᑌᐠ ᐊᓄᑭᐃᐧᓂᐠ ᑫᐃᔑᐸᑕᑭᑌᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ. ᐁᑲᐧ ᐅᐅᐁᐧ ᑐᒋᑲᑌ ᑐᑲᐣ ᒪᓇᑎᑲᐧᓂᐊᐧᐣ, ᐸᐡᑯᓂᑲᓂᐊᐧᐣ, ᓴᑲᐦᐃᑲᓂᐊᐧᐣ, ᐅᑕᐱᓂᑲᑌᐊᐧᐣ ᑲᐱᐃᐧᓯᑭᐣ ᑫᑯᓇᐣ, ᒥᓇ ᒥᑲᓇᐣ ᐅᔑᒋᑲᑌᐊᐧᐣ ᒋᐅᒋᔕᓂᐊᐧᐠ ᑲᐃᔑᐊᓄᑭᓇᓂᐊᐧᐠ.


Picture3.jpg

STEP 3 | SUBSTATION PAD CONSTRUCTION
ᑕᐦᑯᑭᐃᐧᐣ 3 | ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ ᑲᐃᔑᐸᑕᑭᑌᐠ ᒋᐅᔑᒋᑲᑌᐠ

The top soil on site is stripped to remove any unsuitable native material. Imported fill is then brought in and placed to build up the substation pad. This is completed with heavy equipment.

ᐁᑲᐧ ᐊᐦᑭ ᐊᐧᑭᑕᑲᒥᐠ ᑲᐊᔭᐠ ᐸᐡᑯᐁᐧᐸᐦᐃᑲᑌ ᑭᐡᐱᐣ ᐁᑲ ᑲᑭᔭᐸᑕᐠ ᐅᐅᐁᐧ ᐊᐦᑭ. ᐁᑲᐧ ᐸᑲᐣ ᓀᑲ ᐱᑐᒋᑲᑌ ᑫᔭᐸᑕᐠ ᐊᐱᐣ ᑲᐃᐧᐅᔑᒋᑲᑌᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ. ᐁᑲᐧ ᑭᒋᐅᑕᐸᓇᐠ ᐊᐸᑎᓯᐊᐧᐠ ᐅᐅᐁᐧ ᑲᑐᒋᑲᑌᐠ.


Picture4.png

STEP 4 | BELOW GRADE FACILITIES
ᑕᐦᑯᑭᐃᐧᐣ 4 | ᒐᐸᔑᐢ ᐊᐸᒋᒋᑲᓇᐣ ᑲᐃᐧᐊᒋᑲᑌᑭᐣ

Heavy equipment is used to install below grade facilities such as conduits, ground grids and cable trenches.

ᑭᒋᐅᑕᐸᓇᐠ ᐊᐸᑎᓯᐊᐧᐠ ᐊᐱᐣ ᐅᑫᐧᓂᐊᐧᐣ ᓇᓇᑲ ᑫᑯᓇᐣ ᑲᐃᐧᐊᒋᑲᑌᑭᐣᐦ ᑐᑲᐣ ᐱᐊᐧᐱᑯ ᐊᐸᒋᒋᑲᓇᐣ ᒥᓇ ᓇᐸᐱᑫᓂᑲᓂᔭᐱᐣ ᐱᒪᐣᑲᓂᐠ ᑲᐃᐧᐊᒋᑲᑌᑭᐣ.


Picture5.jpg

STEP 5 | FOUNDATIONS
ᑕᐦᑯᑭᐃᐧᐣ 5 | ᑫᐃᔑᐸᑕᑭᑌᑭᐣ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᔕᐣ

There are three types of foundations typically installed in a substation: helical piles installed with an excavator; driven piles installed with a large piling rig; and concrete cast-in-place type foundations where carpenters frame up forms and pour concrete to create the foundation.

ᐁᑲᐧ ᓂᔕᐧᔦᑭᓇᑲᐧᓄᐣ ᑲᐃᔑᐊᒋᑲᑌᑭᐣ ᐅᑫᐧᓂᐊᐧᐣ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᔕᐣ: ᐁᑲᐧ ᐃᐡᑯᑌᐤ ᐊᐸᒋᒋᑲᓇᐣ ᐊᒋᑫᐃᐧᐣ ᑭᒋᐅᑕᐸᐣ ᐊᐸᑎᓭ; ᐁᑲᐧ ᒥᓇ ᑯᑕᑭᔭᐣ ᑭᒋᐱᐊᐧᐱᑯᐣ ᐊᒋᑲᑕᐊᐧᓄᐣ; ᒥᓇ ᐊᓯᓂᑲᐣ ᑲᐃᔑᐊᑌᑭᐣ ᑕᐱᐡᑯᐨ ᒥᑎᑯᓇᐯᐠ ᐃᐃᒪ ᑲᑭᐃᔑᑲᐧᔭᒋᒋᑫᐊᐧᐨ ᒥᓇ ᑫᐃᔑᓯᑭᓂᑲᑌᐠ ᐅᐅᐁᐧ ᐊᓂᓯᑲᐣ ᑫᐃᔑᐊᑌᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ.


Picture6.jpg

STEP 6 | STRUCTURAL STEEL SUPPORT
ᑕᐦᑯᑭᐃᐧᐣ 6 | ᐱᐊᐧᐱᐠ ᑲᔭᐸᑕᐠ ᒋᒥᒋᒥᓂᑫᒪᑲᐠ

Structural steel will come in two styles: H-beam, which is large, made of fewer pieces and easier to install; and tubular, which is very similar to h-beam but tubular in form. The steel is then secured to the foundations.

ᐁᑲᐧ ᐱᐊᐧᐱᐠ ᑲᔭᐸᑕᐠ ᑕᓂᔕᐧᔦᑭᓇᑲᐧᓄᐣ: ᑐᑲᐣ ᒋᓂᑭᑐᓇᑲᐧᐠ, ᒥᓇ ᒥᔕ, ᐁᑲᐧ ᐸᐱᑭᐢ ᑫᑯᓇᐣ ᐊᐸᑕᓄᐣ ᒥᓇ ᐁᐧᑕᐣ ᑲᓇᐱᓂᑲᑌᐠ; ᒥᓇ ᑯᑕᐠ, ᑫᑲᐟ ᐯᔑᑲᐧᐣ ᐃᔑᓇᑲᐧᐣ ᔕᑯᐨ ᐅᒋᒪᔭᑭᓇᑲᐧᐣ. ᐁᑲᐧ ᐊᐱᐣ ᐱᐊᐧᐱᑯᐣ ᑲᐧᔭᐠ ᓯᑕᐦᐃᑲᑌᐊᐧᐣ ᐃᐃᒪ ᑲᐃᐧᐃᔑᐸᑕᑭᑌᑭᐣ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᔕᐣ.


Picture7.jpg

STEP 7 | ELECTRICAL EQUIPMENT
ᑕᐦᑯᑭᐃᐧᐣ 7 | ᐃᐡᑯᑌᐤ ᐊᐸᒋᒋᑲᓇᐣ

Major electrical components are installed on the structural steel and foundations. This includes power transformers, breakers, reactors and control buildings trucked in and installed with large cranes.

ᐁᑲᐧ ᑭᒋᐃᐡᑯᑌᐤ ᐊᐸᒋᒋᑲᓇᐣ ᐊᑯᑲᒋᑲᑌᐊᐧᓄᐣ ᐅᐅᒪ ᐱᐊᐧᐱᑯ ᒥᑎᑯᑲᓂᐠ ᒥᓇ ᑲᐃᐧᐃᔑᐸᑕᑭᑌᑭᐣ. ᐁᐦᐊᐠ ᑲᔦ ᐃᐡᑯᑌᐊᐧᑭᑯᓴᐠ, ᑭᐱᒋᐁᐧᐱᓂᑲᓇᐠ, ᒪᒋᐁᐧᐸᐦᐃᑲᓇᐠ ᒥᓇ ᑯᑕᑭᔭᐣ ᑫᑯᓇᐣ ᑲᔭᐸᑕᑭᐣ ᐊᒋᑲᑌᐊᐧᓄᐣ ᐁᑲᐧ ᑭᒋᐅᐸᑕᐣ ᑲᑭᒋᑭᓇᐧᑯᓂᑫᐨ ᐊᐸᑎᓯᐊᐧᐠ.


STEP 8 | ELECTRICAL BUS WORK
ᑕᐦᑯᑭᐃᐧᐣ 8 | ᐃᐡᑯᑌᐤ ᐸᐢ ᐊᓄᑭᐃᐧᐣ

Once all electrical equipment is installed, and depending on the design of the station, the crew will install the flexible and rigid bus. This is a labour-intensive process, performed manually with manlifts and cranes.

ᐁᑲᐧ ᑲᑭᓇ ᐃᐡᑯᑌᐤ ᐊᐸᒋᒋᑲᓇᐣ ᐃᐡᑲᐧ ᐊᑯᑲᒋᑲᑌᑭᐣ, ᐊᓂᐣ ᐅᑕ ᒪᔭᑦ ᑫᐃᔑᓇᑲᐧᐠ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ, ᐁᑲᐧ ᐊᓄᑭᓇᑲᓇᐠ ᑲᐧᔭᐠ ᐅᑲᓇᓇᑲᒋᑐᓇᐊᐧ. ᐁᑲᐧ ᒪᐊᐧᐨ ᐅᐅᐁᐧ ᐊᓄᑭᐃᐧᐣ ᑭᒋᐊᓄᑭᐁᐧᐣᑕᑲᐧᐣ, ᑕᒧᒋᑐᒋᑲᑌ ᐱᑯ ᑐᑲᐣ ᑭᒋᐅᑕᐸᓇᐠ ᒋᐊᐸᑎᓯᐊᐧᐨ.


STEP 9 | CABLE PULLING & TERMINATING
ᑕᐦᑯᑭᐃᐧᐣ 9 | ᓇᐸᐱᑫᓂᑲᓇᐣ ᐃᐧᑯᐱᒋᑫᐃᐧᐣ & ᐅᑕᐱᓂᑲᑌᐊᐧᐣ

All previously installed major equipment is wired to bring the system online and functionally operational. Cables are pulled to each piece of equipment from the control building and terminated.

ᐁᑲᐧ ᑲᑭᓇ ᑭᒋᐊᐸᒋᒋᑲᓇᐣ ᑭᓇᐸᐱᑫᓂᑲᑌᐊᐧᓄᐣ ᒋᐊᓄᑭᒪᑲᐠ ᐅᐅᐁᐧ ᐊᐧᑌᓂᑲᓂᔭᑊ ᒥᓇ ᒋᐊᓄᑭᓭᐠ. ᐁᑲᐧ ᓇᐸᐱᑫᓂᑲᓂᔭᐱᐣ ᐅᐅᒪ ᐊᐸᒋᒋᑲᓂᐠ ᐸᐯᔑᐠ ᐃᐧᑯᐱᒋᑲᑌᐊᐧᓄᐣ ᐅᐅᒪ ᑲᑭᐅᒋᐅᔑᒋᑲᑌᐠ ᐊᓄᑭᐃᐧᓂᐠ ᐁᑲᐧ ᐊᐱᐣ ᐅᑕᐱᓂᑲᑌ.


STEP 10 | TESTING & COMMISSIONING
ᑕᐦᑯᑭᐃᐧᐣ 10 | ᓇᓇᑲᒋᒋᑫᐃᐧᐣ & ᐊᓄᑭᑲᒋᑫᐃᐧᐣ

The final stage involves technicians performing tests to ensure all equipment will function when energized. Once this is completed, the substation is turned on and begins to provide power to communities.

ᐁᑲᐧ ᐃᐡᑲᐧᔭᐨ ᐅᑫᐧᓂᐊᐧᐠ ᑭᒋᐊᓄᑭᓇᑲᓇᐠ ᐅᑲᑫᐧᒋᑐᓇᐊᐧ ᑫᒋᓇᐨ ᑲᑭᓇ ᑫᑯᐣ ᒋᐊᓄᑭᓭᑭᐣ ᐁᑲᐧ ᐊᐱᐣ ᒋᐃᐡᑯᑌᐁᐧᐸᐦᐃᑲᑌᐠ. ᐁᑲᐧ ᐊᐱᐣ ᑭᔑᒋᑲᑌᐠ, ᐅᐅᐁᐧ ᐃᐡᑯᑌᐃᐧᑲᒥᑯᐢ ᑕᐃᐧᓂᑲᑌ ᐁᑲᐧ ᐊᐱᐣ ᐃᐡᑯᑌᓂ ᒥᓇᑲᓄᐊᐧᐠ ᑕᔑᑫᐃᐧᓇᐣ.